Project Schedule

Environmental Agency Meeting October 2003
Project Kick-off Meeting March 15, 2004
Meetings with Agencies and Groups As scheduled, When required
Alternatives Information Meeting August 4, 2005
Preferred Alternative Presentation
to the Board of County Commissioners
September 13, 2005
Consensus Alignment Presentation to the Board of County Commissioners January 24, 2006
Design and Right-of-Way Acquisition  To follow completion of Preliminary Engineering Study
Construction In accordance with the following schedule, as established by the joint Florida Department of Transportation/St. Johns County Agreement.

Required
Construction Start
Required
Completion Year
North Segment: Racetrack Rd to CR 210 2009 2011
Central Segment: CR 210 to SR 16 2010 2012
South Segment:  SR 16 to CR 208 2015 2017